In [Click to configure] select [PR relations]. To relate processes with specific results, complete the following configuration.

Step 1. List all the items

List all the results that belong to each process previously configured, e.g: Machine1 produces: Prod1, Prod2 & Prod3.

Step 2. Enter the list in edinn

    1. Process: configure process by process, of those available in the dropdown.
    2. Result: enter a record for each relationship between the process and a result selected in <CLICK HERE>
    3. Configure the OEE for the relation if needed.

Step 3. Save changes

    1. Press to insert in the table the configuration of the status. Repeat this action for each status to add.