This report performs a simulation and shows the autocontrol tasks that will be launched in the future. It is very useful to predict the work load of tomorrow, next week, next month, a special period, etc.

Selectors are:

    • Please see: "Common aspects"
    • Type: the type of autocontrol task that you want to simulate.
    • Contains: simulate only those tasks that contain certain text. You can put != at the beginning to indicate to select those records which do not contain the indicated text.
    • Interval: to simulate future periods, the report needs to know the interval of the simulation. The shorter the period, the more precise the simulation, but it will take much longer to calculate the report.
    • Critical: if the tasks to simulate are only the critical ones.
    • Team: if you want to simulate only tasks relative to a specific team.

Note: For those tasks which are programmed by production quantity, the system will take into account the nominal speed multplied by the OEE, different than zero, of the longest period.